Parking Garage Update Week 5

Week of August 30, 2021Work Schedule For the week of August 30, Tenet Construction will be working on level 4 and will be performing sealant removal & replacement and related concrete repairs (Work Zone Spaces). As a precaution (which will continue through the project), we are going to be blocking off spaces on the 3rd…

Read More

Parking Garage Update Week 4

Week of August 23, 2021Work Schedule For the week of August 23, Tenet Construction will be working on level 4 and will be performing sealant removal & replacement and related concrete repairs (Work Zone Spaces). As a precaution (which will continue through the project), we are going to be blocking off spaces on the 3rd…

Read More

Parking Garage Update Week 3

Week of August 16, 2021Work Schedule For the week of August 2, Tenet Construction will be working on level 5 and will be performing sealant removal & replacement and related concrete repairs. As a precaution (which will continue through the project), we are going to be blocking off spaces on the 4th level as well…

Read More