Parking Garage Update Week 3

Week of August 16, 2021Work Schedule For the week of August 2, Tenet Construction will be working on level 5 and will be performing sealant removal & replacement and related concrete repairs. As a precaution (which will continue through the project), we are going to be blocking off spaces on the 4th level as well…

Read More

Parking Garage Update Week 2

Week of August 2, 2021Work Schedule For the week of August 2, Tenet Construction will be working on level 5 and will be performing sealant removal & replacement and related concrete repairs. As a precaution (which will continue through the project), we are going to be blocking off spaces on the 4th level as well…

Read More

Parking Garage Update Week 1

Week of July 26, 2021Work Schedule The Renaissance Garage Project will begin this week. There are some important areas of the garage for you to be aware during the duration of the project. Some of these areas may not be utilized for the project at the start but are designated as such for the project:…

Read More

Pet Update

Please refrain your pets from doing their duty on private property, the common grounds, especially in the park. When walking your pet in our community remember it should be leashed. Also, it is important to remember to immediately clean up after your pet.

Read More

Community Update 2017

Safety FirstPlease be mindful of the speed limit in our community and always stop at the stop signs. With the start of another school year,school buses are back on the road. Please be mindful of children, entering and exiting school buses to avoid any accidents and injuries. When a school bus makes a stop to…

Read More