Parking Garage Update Week 8

Week of September 20, 2021
Work Schedule

For the week of September 20, Tenet Construction will be working on level 3 and will be performing sealant removal & replacement and related concrete repairs (Work Zone Spaces). As a precaution (which will continue through the project), we are going to be blocking off spaces on the 2nd level as well to protect vehicles and property from falling debris (Fall Zone Spaces).


The spaces for the coming week will be blocked off on Wednesday evening and will remain blocked off until the work in that area is completed (September 22nd). This work is impacting Hunt to Find Spaces so you keep that in mind as you are looking for parking places as you may need to go to the upper level to find spaces. This work also impacts Reserved spaces belonging to Condo Owners.


Work Zone Spots – 202-216
Fall Zone Spots – 137-151

https://www.mainstreetmanagementllc.com/wp-content/uploads/2021/09/Week-of-September-20-Impacted-Spot-Map.pdf