Rennaissance Parking Garage Updates

Read below for important updates regarding the Rennaissance Place parking garage improvement project. 

Summary of Parking Garage Repair & Maintenance Project

The Project is scheduled to start again on May 16th.

Tenet Construction is the firm that will be performing the work.  They are located in Columbus, OH and more information about them can be found at https://tenetcs.com/.

RP Parking Facility, LLC (Owner of Garage) has contracted with Arsee Engineering (http://www.arsee-engineers.com/) to serve as the Consulting Engineer for this project and will assist on the administration of the construction work.

WHEN WILL WORK BE DONE?

It is projected that this project should be completed by the end of July. With the current economic climate, lead time on materials and supplies could impact the completion date.  The project could also be impacted by weather.  Your patience and understanding is greatly appreciated.

Majority of the work will be completed during the evening hours while the garage is less populated so please be aware of workers, debris and other items related to the project when driving in the garage.

WHAT WILL BE REPAIRED?

There are several areas that we will be addressing during this project but here is an overview of the type of work that is being addressed:

  • Concrete repairs in vertical and overhead areas
  • Remove and replace joint sealants
  • Repair cracks in concrete
  • Remove and replace traffic-bearing membrane systems
  • Power washing and re-striping

DURING THE PROJECT

It is important to keep in mind that this project is a process.  We will be removing joint sealants between each slab, inspecting, and repairing and then replacing the sealant.  Therefore, there could be times where water flow is greater if we get rain and that it could be worse before it is better and for that to be kept in mind as the project moves forward.

Please bookmark this webpage as this will be the mode of communication about the project and will be updated with the latest information including areas that are targeted for work so your parking location may be impacted, and you will need to park in different areas if your reserved space is being impacted by this project.

Weekly Parking Garage Update

Parking Garage Update Week 16

By Mainstreet Management | May 18, 2022

For Week 16 (May 23 – May 25), work will continue in areas that do not require cars to be moved.  The Contractor is still dealing with material delays.  Even though cars do not need to be moved, there will be significant dust with the work that is being performed. 

Once we get an update on material availability from the Contractor, we will update the schedule accordingly.

Please stay tuned to this website for updates.