Rennaissance Parking Garage Updates

Read below for important updates regarding the Rennaissance Place parking garage improvement project. 

Summary of Parking Garage Repair & Maintenance Project

The Project is scheduled to begin on July 26th.

Tenet Construction is the firm that will be performing the work.  They are located in Columbus, OH and more information about them can be found at https://tenetcs.com/.

RP Parking Facility, LLC (Owner of Garage) has contracted with Arsee Engineering (http://www.arsee-engineers.com/) to serve as the Consulting Engineer for this project and will assist on the administration of the construction work.

WHEN WILL WORK BE DONE?

It is projected that this project should be completed by the end of October.  With the current economic climate, lead time on materials and supplies could impact the completion date.  The project could also be impacted by weather.  Your patience and understanding is greatly appreciated.

Majority of the work will be completed during the evening hours while the garage is less populated so please be aware of workers, debris and other items related to the project when driving in the garage.

WHAT WILL BE REPAIRED?

There are several areas that we will be addressing during this project but here is an overview of the type of work that is being addressed:

  • Concrete repairs in vertical and overhead areas
  • Remove and replace joint sealants
  • Repair cracks in concrete
  • Remove and replace traffic-bearing membrane systems
  • Power washing and re-striping

DURING THE PROJECT

It is important to keep in mind that this project is a process.  We will be removing joint sealants between each slab, inspecting, and repairing and then replacing the sealant.  Therefore, there could be times where water flow is greater if we get rain and that it could be worse before it is better and for that to be kept in mind as the project moves forward.

Please bookmark this webpage as this will be the mode of communication about the project and will be updated with the latest information including areas that are targeted for work so your parking location may be impacted, and you will need to park in different areas if your reserved space is being impacted by this project.

Weekly Parking Garage Update

Parking Garage Update

By Charsha Hayden | July 21, 2021

Week of July 26, 2021
Work Schedule

The Renaissance Garage Project will begin this week. There are some important areas of the garage for you to be aware during the duration of the project. Some of these areas may not be utilized for the project at the start but are designated as such for the project:

Spot 17 – The Porta-John for the workers will be placed in this location (see location on map – Basement).
Spots 265-267 – This is the designated location for storage of material and supplies (see location on map – 4th level)

For the week of July 26, Tenet Construction will be working during the day on 3 types of mock-ups that will be used throughout the project. The purpose of the mock-up is to perform work following a process to arrive at the desired result. These mock-ups will be approved and then these processes will be followed through the project to ensure proper methods are followed, utilization of the correct material and supplies and that the desired result is achieved. They will be doing a mock-up on partial depth, vertical and overhead patch.

The parking spots that will be impacted during this week are 296 – 301 (5th level) and 237-241 (4th level).

https://www.mainstreetmanagementllc.com/wp-content/uploads/2021/06/Week-of-July-26-Impacted-Spot-Map.pdf

Parking Garage Reference Documents

Parking Updates Archive