Rennaissance Parking Garage Updates

Read below for important updates regarding the Rennaissance Place parking garage improvement project. 

Summary of Parking Garage Repair & Maintenance Project

The Project is scheduled to start again on May 16th.

Tenet Construction is the firm that will be performing the work.  They are located in Columbus, OH and more information about them can be found at https://tenetcs.com/.

RP Parking Facility, LLC (Owner of Garage) has contracted with Arsee Engineering (http://www.arsee-engineers.com/) to serve as the Consulting Engineer for this project and will assist on the administration of the construction work.

WHEN WILL WORK BE DONE?

It is projected that this project should be completed by late Fall 2022. With the current economic climate, lead time on materials and supplies could impact the completion date.  The project could also be impacted by weather.  Your patience and understanding is greatly appreciated.

Majority of the work will be completed during the evening hours while the garage is less populated so please be aware of workers, debris and other items related to the project when driving in the garage.

WHAT WILL BE REPAIRED?

There are several areas that we will be addressing during this project but here is an overview of the type of work that is being addressed:

  • Concrete repairs in vertical and overhead areas
  • Remove and replace joint sealants
  • Repair cracks in concrete
  • Remove and replace traffic-bearing membrane systems
  • Power washing and re-striping

DURING THE PROJECT

It is important to keep in mind that this project is a process.  We will be removing joint sealants between each slab, inspecting, and repairing and then replacing the sealant.  Therefore, there could be times where water flow is greater if we get rain and that it could be worse before it is better and for that to be kept in mind as the project moves forward.

Please bookmark this webpage as this will be the mode of communication about the project and will be updated with the latest information including areas that are targeted for work so your parking location may be impacted, and you will need to park in different areas if your reserved space is being impacted by this project.

Weekly Parking Garage Update

IMPORTANT CHANGE TO SCHEDULE

By Mainstreet Management | August 9, 2022

August 4, 2022

Attached is a revised map and updated schedule related to the improvements being made to the Renaissance Parking Garage.  We understand that this is an inconvenience for all of us but we appreciate your patience and understanding as we do these critical repairs to the garage for the overall safety and integrity of the garage.

During the scheduled work reported earlier, Tenet Construction and our Engineering firm found some additional work that needed to be done on the upper crossovers (Level 4 & 5).  This additional work is going to keep the Level 4 section closed until August 16.  At that time, we will be able to open that level for parking as they move to the crossover on Level 5 which will remain closed until August 23 and then be open for parking.

The attached updated schedule & map shows the work areas that will be impacted, and this work is scheduled to run through September 20.  Once the crossover work is completed on Levels 4 & 5, Tenet Construction will then move down the garage dealing with all the crossover sections as outlined.  The traffic around the turns in the garage will be reduced to one lane so it is CRITICAL that you be careful and remain patient during this process.  Please be aware of workers and other vehicles as the traffic patter will be different than what you are used to.

There is additional work that will need to be completed once these issues are addressed and we will continue to update this website with any pertinent changes or notices.  Thanks for your continued support and understanding as this project continues to move forward.