Parking Garage Update Week of March 20, 2023

For the week of March 27 – April 2, Tenet Construction will be finish cutting the riglet and begin coating preparation and installing coating on interior wash areas of the garage and interior turn lanes. There will be no spots closed during this week but the spots listed below will be impacted as these spots…

Read More

Parking Garage Update Week of March 13, 2023

Thank you for your patience and understanding as we continue to work on the garage repairs. For the week of March 20, Tenet Construction will be working on the final phase of caulking and concrete repairs on the East Side of level 1 and 2. This will included all vertical cove and wash repairs and…

Read More